Variation Notice Template — Construction (Australia)
By Cal Crane — founder, TradeControl; Operations Manager, Barzen Projects
A variation notice tells the builder, in writing, that you consider particular work a change to your contracted scope — before or as the work is done, not after the argument starts. It is commercial correspondence, not a legal document. It records the instruction received, the changed scope, the price basis and the time impact.
General information only — not legal advice. This template is commercial correspondence between you and the builder. Your contract governs how variations must be notified, priced and approved — check its variation clause for any required form, timing or approval steps before relying on any template. Where the value or risk is significant, speak to a construction lawyer.
What the notice must capture
A variation argument is usually lost on missing detail, not on the principle. The template includes the fields that matter:
- Project and contract reference
- Date of the notice
- Instruction received — who gave it, when, and whether it was verbal or written
- Description of the varied work and why it is outside the contracted scope
- Price basis — quotation, dayworks, or schedule of rates
- Estimated cost
- Time impact
- Attachments — photos, day labour docket references, marked-up drawings
- Approval signature block
Notify before the work, not after the argument
The value of a variation notice is its timing. Issued before or during the work, it puts the builder on notice while the decision to proceed is still theirs, and it records the instruction while everyone remembers giving it. Issued after the account is queried, it reads as an afterthought — and by then the site personnel who gave the instruction may be gone.
No written instruction? Docket the work the day it happens. A day labour docket signed by the builder's representative on the day is the contemporaneous record that supports the notice.
Where TradeControl fits
TradeControl's SOW scope queries let a supervisor check, from the phone, whether instructed work sits inside or outside the contracted scope of works before agreeing to anything — and Day Dockets capture the labour, materials and the builder's signature on the day. See the full feature set.
Related
- Day labour docket template — no written instruction? Docket the work the day it happens
- Security of Payment (NSW) guide
TradeControl provides commercial support tools only. It does not provide legal advice.